PDU8000 Modular Precision PDC V2.0
User Manual
6.1 Check Before Power-on Commissioning
Table 6-1 Hardware installation checklist
No.
1
2
3
4
5
Table 6-2 Electrical connection checklist
No.
1
2
3
4
5
Issue 04 (2021-04-13)
6
Check Item
The cabinet is clean, without redundant screws,
copper wires, or other debris.
The paint on the cabinet exterior is intact.
The cabinet door and lock work properly.
All labels are correct, clear, and complete.
The surrounding area of the cabinet contains no
waste tape, cable ties, paper, or packing materials.
Check Item
All cables are connected properly.
The ground cable is connected properly.
The excessive sections of ground cables and power
cables are cut off.
Phase cables are connected properly.
All circuit breakers are OFF.
Copyright © Huawei Technologies Co., Ltd.
Commissioning Guide
6 Commissioning Guide
Result
□Yes □No
□Yes □No
□Yes □No
□Yes □No
□Yes □No
Result
□Yes □No
□Yes □No
□Yes □No
□Yes □No
□Yes □No
68