Power-On Commissioning - Huawei PDU8000 User Manual

Modular precision pdc
Hide thumbs Also See for PDU8000:
Table of Contents

Advertisement

PDU8000 Modular Precision PDC V2.0
User Manual
Table 6-3 Cable installation checklist
No.
1
2
3
4
5
6

6.2 Power-On Commissioning

Context
● The power-on commissioning process requires at least two qualified
● Cautions and warnings must be properly placed onsite.
● Users are categorized as admin and operator. Admin users have more rights
● Powering off the PDC disconnects the power supply to the downstream devices.
Procedure
Step 1 Check cable connections and the mechanical performance.
1.
2.
Issue 04 (2021-04-13)
Check Item
All bolts are tightened, especially the bolts used for
electrical connection. Flat washers and spring
washers are installed properly.
Cable installation meets the cable routing
requirements.
Cables are routed in the way convenient for future
maintenance and expansion.
There are no unnecessary adhesive tape or cable
ties on the cables.
Exposed parts near the wiring terminals and lugs
are wrapped in PVC insulation tape or heat
shrinking tubing.
The cable routing for power cables and monitoring
cables meets the requirements for routing power
cables and signal cables and complies with the
cable routing plan.
NO TICE
electricians, one responsible for operations and the other for monitoring.
than operator users.
Exercise caution with this operation when the PDC is supplying power to a
working system.
Check that cables are connected correctly outside the cabinet. Check that all
bolts are secured for inlet and outlet cables and tighten a bolt if it is loose.
Check that ground cables are properly connected.
Copyright © Huawei Technologies Co., Ltd.
6 Commissioning Guide
Result
□Yes □No
□Yes □No
□Yes □No
□Yes □No
□Yes □No
□Yes □No
69

Advertisement

Table of Contents
loading

Table of Contents