Installation Verification - Huawei FusionDC1000A Installation Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionDC1000A:
Table of Contents

Advertisement

FusionDC1000A Prefabricated All-in-One Data
Center
Installation Guide (IT Scenario)
After the FusionDC1000 is installed, you need to verify the installation.
Table 11-1 Post-installation checklist
No.
1
2
3
4
5
Issue 01 (2021-04-20)
11
Check Item
Pre-fab. module
installation
Equipment
appearance
Water pipe
connections
Thermal insulation
layers on water
pipes
External grounding
Copyright © Huawei Technologies Co., Ltd.

Installation Verification

Check
Expected Result
Method
Observe
The installation conforms to the
design requirements.
Observe
● The equipment is intact and free
from inclination, distortion, pain
drop, and rust.
● All connections are secure.
Observe
Water pipes are securely connected.
Observe
All pipes are seamlessly wrapped with
thermal insulation layers.
Observe
● Each pre-fab. module has at least
two ground points and is grounded
securely with a ground resistance
of 10 ohms or less.
● Each row of cable trays has at least
two ground points and is grounded
securely with a ground resistance
of 10 ohms or less.
11 Installation Verification