FusionDC1000A Prefabricated All-in-One Data
Center
Installation Guide (IT Scenario)
Step 2 Lift the awning and insert it into the U-shaped slot in the awning mounting plate
from above the mounting plate.
Step 3 Insert a rubber pad between the bottom of the awning and the mounting plate.
Install screws on both sides and three screws on the top of the awning to partially
secure the awning.
Figure 5-4 Installing an awning
Step 4 (Optional) If the awning is unstable after being partially secured, install washers.
Issue 01 (2021-04-20)
NO TE
● A certain number of washers can be installed onsite based on the actual situation to
ensure that the awning is securely installed and does not affect the fireproof door
operation.
● When installing a holeless washer, tighten the screw to prevent the washer from falling
off.
Copyright © Huawei Technologies Co., Ltd.
5 Installing External Accessories for the Pre-fab.
Module
52