FusionDC1000A Prefabricated All-in-One Data
Center
Installation Guide (IT Scenario)
Figure 8-27 Cable interconnection position
Step 7 Install the electromagnetic valve.
Do not install the electromagnetic valve when installing the fire cylinder for the first time. Install
the electromagnetic valve when commissioning the fire extinguishing system.
1.
----End
Issue 01 (2021-04-20)
NO TE
Remove the protective cover at the electromagnetic valve installation position
on the container valve. Align the electromagnetic valve and the container
valve, and tighten the electromagnetic valve clockwise.
Figure 8-28 Removing the electromagnetic valve protective cover
Copyright © Huawei Technologies Co., Ltd.
8 Installing Devices Inside the Pre-fab. Module
89

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r021c00

Table of Contents