FusionDC1000A Prefabricated All-in-One Data
Center
Installation Guide (IT Scenario)
No.
6
7
8
9
Issue 01 (2021-04-20)
Check Item
Cable connections
Cable binding
Installation of
external
accessories
Labels
Copyright © Huawei Technologies Co., Ltd.
Check
Expected Result
Method
Observe
● All cable connections are secure,
especially network cable
connections.
● Bear cables and terminal barrels
near wearing terminals are
wrapped in insulation tape or heat
shrink tubing.
● Flat washers and spring washers of
all wiring terminals are securely
installed.
● Cables are routed in the way
convenient for future maintenance
and expansion.
● Cabinets are clean and have no
dust, excessive cable ties, cable
cuts, or other foreign matter inside.
Observe
● Cables are neat and not coiled, and
excessive parts are cut.
● Cable ties do not overlap, and the
joints are evenly cut without burrs.
● Cables are placed properly and not
tense at turning points.
● Cable routes are straight and
smooth, and do not intersect inside
a cabinet.
Observe
The number and positions of external
accessories installed conform to
design requirements.
Observe
All labels are correct, clear, and
complete.