Commissioning The Emergency Light (Ce) - Huawei FusionModule1000A20 Commissioning Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A20:
Table of Contents

Advertisement

FusionModule1000A20 Prefabricated All-in-One
Data Center
Commissioning Guide
Skill requirement: fire engineer
Procedure
Step 1 Switch on the input power circuit breaker of the extinguishant control panel or
connect the extinguishant control panel batteries to power on the extinguishant
control panel.
Step 2 Flip the key to Enable Control rightward, and set the access level of the
extinguishant control panel to 2.
Step 3 Press Silence/Sound Alarm to start or abort the fire alarm bell.
Step 4 Press Alarm/Fault Warning Silence to silence the fault noise generated by the
extinguishant control panel.
Step 5 Press Reset to reset the extinguishant control panel, and reset the key to Enable
Control by flipping it leftward.
----End

9.4.1.2 Commissioning the Emergency Light (CE)

Prerequisites
The sockets of the emergency light have been powered on.
Preparations
Tools: step ladder, Phillips screwdriver
Documents: power supply and distribution system diagram, fire extinguishing
device layout diagram (CE)
Skill requirement: fire engineer
Procedure
Step 1 Turn off the upstream switch of the emergency light power cable.
Issue 03 (2022-12-15)
NO TE
For the diagrams, see the initial configuration parameter manual for the solution in use.
NO TE
For the diagrams, see the initial configuration parameter manual for the solution in use.
Copyright © Huawei Digital Power Technologies Co., Ltd.
9 Commissioning Core Components
108

Advertisement

Table of Contents
loading

Table of Contents