FusionModule1000A20 Prefabricated All-in-One
Data Center
Commissioning Guide
Skill requirement: fire engineer
Procedure
Step 1 Switch on the input power circuit breaker of the extinguishant control panel or
connect the extinguishant control panel batteries to power on the extinguishant
control panel.
Step 2 Flip the key to Enable Control rightward, and set the access level of the
extinguishant control panel to 2.
Step 3 Press Silence/Sound Alarm to start or abort the fire alarm bell.
Step 4 Press Alarm/Fault Warning Silence to silence the fault noise generated by the
extinguishant control panel.
Step 5 Press Reset to reset the extinguishant control panel, and reset the key to Enable
Control by flipping it leftward.
----End
9.4.1.2 Commissioning the Emergency Light (CE)
Prerequisites
The sockets of the emergency light have been powered on.
Preparations
Tools: step ladder, Phillips screwdriver
Documents: power supply and distribution system diagram, fire extinguishing
device layout diagram (CE)
Skill requirement: fire engineer
Procedure
Step 1 Turn off the upstream switch of the emergency light power cable.
Issue 03 (2022-12-15)
NO TE
For the diagrams, see the initial configuration parameter manual for the solution in use.
NO TE
For the diagrams, see the initial configuration parameter manual for the solution in use.