Huawei FusionModule1000A20 Commissioning Manual page 56

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A20:
Table of Contents

Advertisement

FusionModule1000A20 Prefabricated All-in-One
Data Center
Commissioning Guide
Step 6 Blow smoke towards the smoke detector using a smoke pistol until the smoke
detector indicator changes from blinking once every 6s to steady on to trigger a
smoke detector fire alarm.
Figure 7-2 Short-circuiting ZONE1+ and ZONE1−
Figure 7-3 Loop 1 FIRE RELAY indicator on
Step 7 Heat the heat detector using a heat gun until the heat detector indicator changes
from blinking once every six seconds to steady on to trigger a heat detector FIRE
RELAY alarm.
Issue 03 (2022-12-15)
NO TE
If no smoke pistol is available, you can also short-circuit ZONE1+ and ZONE1− terminals on
the extinguishant control panel using a 470-ohm resistor delivered with the extinguishant
control panel to simulate and trigger a smoke detector FIRE RELAY alarm. After short-
circuiting the ZONE1+ and ZONE1− terminals, remove the resistor if an alarm has been
triggered.
NO TE
● A smoke detector loop alarm is triggered, and the loop 1 fire alarm indicator on the
extinguishant control panel is steady on. The fire alarm bell rings.
● Do not clear the alarm and proceed to the alarm simulation for the smoke detector.
Copyright © Huawei Digital Power Technologies Co., Ltd.
7 System Commissioning
49