FusionModule1000A20 Prefabricated All-in-One
Data Center
Commissioning Guide
4.6 Preparing for the Management System Power-On
Commissioning
Prerequisites
The FusionModule1000 has been installed.
Preparations
Tools: network cable tester, Phillips screwdriver, small-sized flat-head screwdriver,
multimeter, ESD wrist strap
Documents: monitoring device layout diagram, monitoring device networking
diagram, management system initial configuration table
Skill requirement: weak-current engineer familiar with the management system
Procedure
Step 1 Understand the layout of monitoring devices by referring to the monitoring device
layout diagram.
Step 2 Understand the connections of the management system by referring to the
monitoring device networking diagram.
Step 3 Understand the initial configurations of the management system by referring to
the management system initial configuration table.
The passwords and parameters must be the same as those in the initial
configuration parameter manual for the solution in use.
----End
4.7 Preparing for the Fire Extinguishing System Power-
On Commissioning
Prerequisites
The FusionModule1000 has been installed.
Issue 03 (2022-12-15)
NO TE
For the diagrams and tables, see the initial configuration parameter manual for the solution
in use.
NO TICE