Hitachi Relion 670 Series Commissioning Manual page 170

Line distance protection
Hide thumbs Also See for Relion 670 Series:
Table of Contents

Advertisement

Section 11
Testing functionality by secondary injection
11.5.8.9
Verifying the case RetripMode = Contact
It is assumed that re-trip without current check is selected, RetripMode = Contact.
1.
Set FunctionMode = Contact
2.
Apply input signal for CB closed to relevant input or inputs 52a_A (B or C).
3.
Apply input signal, or signals for initiation of CCRBRF (50BF).
4.
Verify that phase selection re-trip and back-up trip are achieved after set times.
5.
Disconnect the trip signal(s). Keep the CB closed signal(s).
6.
Apply input signal(s), for initiation of CCRBRF (50BF).
7.
Arrange disconnection of CB closed signal(s) well before set back-up trip time t2.
8.
Verify that back-up trip is not achieved.
9.
Disconnect injected AC and BFI_3P input signals.
11.5.8.10
Verifying the caseFunctionMode = Current or CB Pos
To be made only whenFunctionMode = Current or CB Pos is selected. It is suggested to make the tests
in one phase only, or at three-pole trip applications for just three-pole tripping.
Checking the case with fault current above set value Pickup_PH
The operation shall be as in RetripMode = UseFunctionMode.
1.
Set FunctionMode = Current or CB Pos.
2.
Leave the inputs for CB close inactivated. These signals should not influence.
3.
Apply the fault condition, including initiation of CCRBRF (50BF), with current above the set
Pickup_PH value.
4.
Check that the re-trip, if selected, and back-up trip commands are achieved.
5.
Disconnect injected AC and BFI_3P input signals.
Checking the case with fault current below set value Pickup_BlkCBPos
The case shall simulate a case where the fault current is very low and operation will depend on CB
position signal from CB auxiliary contact. It is suggested that retrip without current check is used, setting
RetripMode = UseFunctionMode Check.
1.
Set FunctionMode = Current or CB Pos.
2.
Apply input signal for CB closed to relevant input or inputs 52a_A (B or C)
3.
Apply the fault condition with input signal(s) for initiation of CCRBRF (50BF). The value of current
should be below the set value Pickup>BlkCBPos
4.
Verify that phase selection re-trip (if selected) and back-up trip are achieved after set times. Failure
to trip is simulated by keeping the signal(s) CB closed activated.
5.
Disconnect the AC and the BFI_3P signal(s). Keep the CB closed signal(s).
6.
Apply the fault and the initiation again. The value of current should be below the set value
Pickup>BlkCBPos.
7.
Arrange disconnection of CB closed signal(s) well before set back-up trip time t2. It simulates a
correct CB tripping.
8.
Verify that back-up trip is not achieved. Re-trip can appear for example, due to selection
RetripMode = Always.
9.
Disconnect injected AC and BFI_3P input signals.
164
© 2017 - 2023 Hitachi Energy. All rights reserved
1MRK506371-UUS Rev. M
M12104-213 v11
M12104-237 v8
M12104-241 v9
M12104-281 v12
Line distance protection REL670
Commissioning manual

Advertisement

Table of Contents
loading

This manual is also suitable for:

Relion rel670

Table of Contents