Figure 6-1 Fusion Network - NEC NEAX 2400 IMX Manual

Fusion network system
Hide thumbs Also See for NEAX 2400 IMX:
Table of Contents

Advertisement

CHAPTER 6
POST INSTALLATION TEST
This chapter covers how to perform installation tests focusing on the Fusion Call Control Signal (denoted in the
remainder of this manual as FCCS) connections, after hardware installation and data assignment. This chapter
describes the following tests:
How to Check Fusion Link by LEDs on an FCH Card
Repair Procedure When LED Indicates Abnormality
FCCS Network Connection Test
FCCS Alternate Routing Test
Fusion and Non-Fusion Connection Test
At the end of this chapter, the Fusion Link Test Sheet is attached. Make photo-copies of the sheet to record the
test results.
In this chapter, explanations are given using the following network numbering as an example.
Node A
NodeA
(self-Node)
STNA
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
TELN: 410000
STN: 2000
FCCS: Fusion Call Control Signal
Note:
The Individual Trunk Access feature is not available for Fusion Trunks. To seize a specific Fusion Trunk,
use the MBCT command to make busy trunks which are not being tested. This command leaves the Fusion
trunk to be tested in an idle state.
1. How to Check Fusion Link by LEDs on FCH Card
Before performing the Fusion link test, be sure to check the Fusion Link LEDs. Refer to
Fusion link is established, the LYR lamp lights green on the FCH (PA-FCHA) circuit card. However, if it re-
mains off, the layer 2 (Link Layer) is not established. If this is the case, follow the repair procedure listed here.
FUSION Network
STN: Physical Station Number

Figure 6-1 Fusion Network

ND-70185 (E)
Get other manuals https://www.bkmanuals.com
Node B
(other Node)
TELN: Telephone Number
NodeB
STNB
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
TELN: 420000
STN: 2000
Figure
6-2. When the
CHAPTER 6
Page 133
Revision 3.0

Advertisement

Table of Contents
loading

Table of Contents