Installation Environment Requirements

The equipment is installed outdoors. The site selection requirements are as
follows:
Issue 02 (2023-09-30)
The equipment is heavy. Ensure that the installation surface is solid enough to
bear the weight of the equipment.
The site is not located in a low-lying land. The ground level of the site is
above the highest water level of that area in history.
The ground is solid without spongy or soft soil, and is not prone to water
accumulation or subsidence.
The site is located in a well-ventilated area.
The site is far away from sources of strong variation, loud noises, and strong
electromagnetic interference.
The site is not above any underground facilities.
The site must be a class C or higher environment (not a class D or E
environment).
The site is far away from dust, cooking fume, harmful gases, and corrosive,
flammable, or explosive objects.
The site is in an open area and at least 10 m away from any obstacles in all
directions.
The site is at least 50 m away from residential areas.
The site temperature is within the range of –25°C to +60°C. If the temperature
exceeds 55°C, the equipment must be installed in a shaded area.
If the equipment is installed in a place with dense vegetation, in addition to
routine weeding, harden the ground under the equipment to prevent weeds
from growing.
Copyright © Huawei Technologies Co., Ltd.
3 Installation Environment Requirements
54