Plc Commissioning; Creating A Simatic S7 Project - Siemens SINUMERIK 804D sl Commissioning Manual

Cnc part 1 nck, plc, drive
Table of Contents

Advertisement

PLC commissioning

7.1

Creating a SIMATIC S7 project

Introduction
It is necessary to create an S7 project for the basic commissioning of the PLC, the Ethernet
and PROFIBUS communication as well as the input/output data areas of the NCK. To do this
you will have to perform the following operations:
• Creating a project
• Inserting a SIMATIC station 300
• Insert NCU 7x0 in HW config
• Configuring the properties of the network interfaces
• Insert machine control panel and hand wheel
What do you need to be aware of?
Loading the PLC via network interface X130 is also possible if the IP address of the Ethernet
interface is known.
Loading an archive may always be carried out if the communication HMI-NCK is available.
Note
Loading the PLC (CP840) is essential for the configuration of the data path for
saving/restoring the drive data.
At the present time, the HW config of the CP840 can ONLY be loaded alone via network.
Loading the CP840 via PROFIBUS DP2 is not yet possible in the SW version currently
described.
CNC Part 1 (NCK, PLC, drive)
Commissioning Manual, 11/2006, 6FC5397-2AP10-2BA0
Note
The toolbox must have been installed.
7
41

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sinamics s120Sinumerik 840de sl

Table of Contents