Commissioning SINAMICS drives
8.9 First commissioning of SINAMICS drive ended
8.9
First commissioning of SINAMICS drive ended
First commissioning of SINAMICS drive ended
You have completed the first commissioning of the SINAMICS drives.
The acceptance of the topology has been successfully completed:
• All upper LEDs of the drive module are illuminating GREEN.
• The lower LEDs of the drive modules always illuminate YELLOW.
Continue with the steps for commissioning the NCK. You have chosen the "Commissioning"
operating area.
92
CNC Part 1 (NCK, PLC, drive)
Commissioning Manual, 11/2006, 6FC5397-2AP10-2BA0