Function Test; Completing Work - Siemens FC361 Series Technical Manual

Fire control panel
Hide thumbs Also See for FC361 Series:
Table of Contents

Advertisement

Commissioning
9
General commissioning steps

9.4.3 Function test

9.4.4 Completing work

100 | 124
Building Technologies
Fire safety
WARNING
Alarming and RT transmission are activated during testing.
You must do the follow:
Inform fire brigade.
Inform owner of the building.
1. Execute lamp test. Refer to chapter 'Lamp test [➙ 75]'.
2. Test each device (detector, MCP, etc.) individually and check the correctness
of the system behavior (e.g. sounder activation, RT fire, RT fault, fire controls,
etc.). Refer to chapter 'Detection test [➙ 73]'.
3. Make sure that the panel is in normal operation, the buzzer and all system
parts are enabled.
a The function test is finished.
1. Check date and time on the panel display. If they are not correct, modify them.
Refer to chapter 'Set date & time [➙ 81]'.
2. Secure the housing cover with a screwdriver.
3. Complete the installation label (top right of the housing) with the commissioning
date.
a The system can now be handed over to the customer.
A6V10421795_en--_g
2016-11-18