Wiring Test - Siemens SENTRON 7KT PAC1600 Equipment Manual

Energy meter
Hide thumbs Also See for SENTRON 7KT PAC1600:
Table of Contents

Advertisement

3.5.5

Wiring test

You can use the wiring test to check whether the energy meter has been installed correctly.
Requirements
In order to run the wiring test, the energy meter must be connected to an active system and
the following conditions must be fulfilled:
• Three-phase system with all phases (V > 187 V AC PH-N)
• Minimum current flow in each phase (> 1% of current transformer full-scale deflection)
• Positive energy flows (normal system in which the inductive load draws power from the
supply)
7KT16 energy meter
Equipment Manual, 09/2020, 2514284147-04
Description
3.5 Three-phase devices 5 A
65

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sentron 7kt16Sentron 7kt pac 1600

Table of Contents