3.3 Unpacking and Acceptance

Procedure
Step 1 Verify that the cabinet package is intact. If any damage is found, notify the carrier
immediately.
Step 2 Remove the packing materials. Check whether the cabinet exterior is in good
condition and free of collision marks or scratches. If any damage is found, notify
the carrier immediately.
Step 3 Check the type and quantity of fittings against the packing list. If some fittings are
missing or do not comply with the models in the packing list, record the
information and contact the supplier immediately.
----End

3.4 Installing Components

● Use insulated tools during installation.
● Only certified engineers are allowed to install, commission, and maintain smart
cooling products. Otherwise, personal injury or device damage may occur, and
the responsible party shall be liable for any faults caused thereby.
● Onsite electricians must be qualified.
● The minimum front maintenance distance is 900 mm.
● During installation, place the packed top panel on the top of the cabinet to
prevent dust from entering the cabinet. Remove the top panel before power-on
commissioning.
Issue 02 (2022-03-30)
Name
Standard
network cable
WARNING
Copyright © Huawei Technologies Co., Ltd.
Technical Requirements
Signal cable, shielded
straight-through cable, 10 m,
MP8-II, CC4P0.5GY(S), MP8-
II, FTP
3 Installation
Remarks
The length is
determined based
on engineering
survey.