IEC 61850 communication engineering
7.6
100
3.1. Ignore Substation Section will not import the "SSD-file" part of the SCD-
file.
3.2. Don't import ... protects the existing IEDs in case the SCD file does not
match the original configuration in PCM600.
3.3. Replace unknown ... can be used when it is known that the file includes
additional IEDs which are needed. The IED of type Generic IEC 61850 IED
is used to integrate these kinds of IEDs in for example the plant structure.
3.4. Click Ignore PCM Object Type to update the IED object(s) in PCM600
from the IED type(s) in the SCD file, disregarding if the IED type(s) in the
SCD file matches the IED object(s) in PM600 or not.
3.5. Start Import when the definition has been completed. A progress window
presents the import procedure.
4.
IEC09000631-1-en.vsd
IEC09000631 V1 EN
Figure 70:
IEC 61850: SCL Import option

Writing communication configuration to IED

IEC communication depends on proper communication configuration in all IEDs that
communicate via IEC 61850. It is not possible to read the communication
configuration from the IED to PCM600.
However it is possible to make a configuration change in one IED, without affecting
the communication engineering. For example, when the Application Configuration
tool configuration is changed, but no changes are done for the instantiation or deletion
of functions that represent a logical node.
When a changed configuration is written to the IED, the user is asked to update the
communication configuration.