1MRK 511 284-UEN A
650 series
Engineering manual
IEC10000172 V1 EN
Figure 76:
Configuring hardware channels directly to the function blocks
IEC10000173 V1 EN
Figure 77:
CMT: Hardware channels appearing in the Communication
Management Tool
2.
Right-click the IED in the plant structure and select Communication
Management to start the Communication management tool.
3.
Select the DNP3 protocol from the new window and click OK.
the design of the two container windows, which open after the selection of
DNP3.
•
The right window shows tabs for possible communication channels.
•
The left window has a drop down menu for signal selection and buttons for
signal movement, see
DNP3 communication engineering
Figure
78.
Section 9
IEC10000172.vsd
IEC10000173.vsd
Figure 78
presents
109