NetCol5000-A 42 kW Air Cooled In-row Precision Air
Conditioner
User Manual
Procedure
Step 1 Remove the bonnet of the low-pressure needle valve shown in
pressure gauge leather hose to the needle valve.
Figure 3-25 Exhausting nitrogen
(1) Low-pressure needle
valve
Step 2 Open the pressure gauge valve. Loud noises of air flow are generated at first and then
disappear gradually.
Step 3 After the air is exhausted, remove the pressure gauge and install the valve bonnet.
Step 4 Continue exhausting nitrogen from the exhaust pipe needle valve and liquid pipe needle valve
by performing
----End
3.9 Connecting Pipelines
Issue 01 (2017-07-27)
(2) Exhaust pipe needle
valve
Step 1–Step
3.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3 Installation Guide
Figure 3-25
and connect the
(3) Liquid pipe needle valve
51