Top Pipe Routing
When routing pipes from the top, do not route the pipes over servers. If unavoidable, take
measures to protect the servers from being affected by pipe leaks.
Step 1 Straighten the water inlet pipe delivered with the air conditioner, and route it from the inside
to the outside through the water inlet hole on the top of the air conditioner.
Figure 3-32 Upward routing of the water inlet pipe
Step 2 Connect the external water inlet pipe based on the actual condition and wrap the pipe with
thermal insulation foam.
----End
Issue 01 (2017-07-27)
The other end is a reserved G 1/2 inch connector with inner screw threads. Connect the other end to
a hose or rigid pipe based on site requirements.
Secure the water inlet pipe inside the cabinet to the left post of the cabinet using cable ties.