10. Connect the signal cable at terminal block -X9.
11. Route the DRIVE-CLiQ cable through the cable bushing from the top into the Basic Line Module,
4.5.11.3

Cable routing for Active Line Connection Modules

For the Active Line Modules, the customer must carry out the following cabling or connection
work:
Table 4- 12
Cable routing
Cable for the line supply (L1, L2, L3, PE)
Signal cables to terminals -X30, -X40, -X50
PROFIBUS cable or PROFINET cable to the Control Unit
DRIVE-CLiQ connections / signal cables to the Control Unit and to the Active Line
Module
Note:
The "Basic rules for cable routing" and "Preparatory steps" described above must be
observed whenever any cabling or connection work is performed!
Cabinet Modules liquid cooled
Equipment Manual, 04/2020, A5E37067587A
continue to the DRIVE-CLiQ connection -X400, -X401, -X402 and connect there.
Checklist for cable routing and connection work for Active Line Connection Modules
Electrical installation
4.5 Connections