Electrical installation
4.5 Connections
Safety and EMC
Dangerous voltage when covers are missing
If covers are missing, live parts may be touched which can result in death or serious injury.
• Mount all covers again that you removed for the cable routing before commissioning the
Note
Internal cabinet wiring
When routing cables, utmost care must be taken not to change any existing internal cabinet
wiring.
Note
EMC-compliant shielding
The shield plates must be re-mounted before the cabinet is commissioned to ensure EMC-
compliant shielding.
The shields of the motor cables must be secured on the EMC shield bus (M70 option), and
the PE cables must be secured on the PE busbar.
4.5.11.2

Cable routing for Basic Line Connection Modules

For the Basic Line Connection Modules, the customer must carry out the following cabling or
connection work:
Table 4- 11
Cable routing
Cable for the line supply (L1, L2, L3, PE)
Signal cables to terminals -X30, -X40, -X50
PROFIBUS cable or PROFINET cable to the Control Unit
DRIVE-CLiQ connections / signal cables to the Control Unit and to the Basic Line
Module
Note:
The "Basic rules for cable routing" and "Preparatory steps" described above must be
observed whenever any cabling or connection work is performed!
100
WARNING
Cabinet Module.
Checklist for cable routing or connection work for Basic Line Connection Modules
Cabinet Modules liquid cooled
Equipment Manual, 04/2020, A5E37067587A
Completed?

Advertisement