Work Procedures - Toshiba Aquilion TSX-101A/I Series Site Planning Manual

Table of Contents

Advertisement

7.4.1.3

Work procedures

The main work procedures are as follows:
Making the frames for resin application
(1)
Marking
1. Determine the installation locations for the gantry and the patient couch (refer to
subsection 5.3 "Layout").
2. Mark off the resin application areas on the floor sections of the determined
installation locations.
Note: Work can be performed efficiently by using the full-scale gauge
(2)
Drilling the anchor holes and removing the floor covering
1. Drill the anchor holes at the marked positions using an electric drill with 24-mm and
18-mm bits.
2. Cut a slit 10 to 15 mm inside the marking line on the floor using a cutter.
3. Remove the floor covering inside the marking line. (Entire area inside the marking
line)
4. Clean the area from which the floor covering has been removed.
Marking off the floor
Drilling the anchor holes
Removing the floor covering
Applying resin
Finishing (forming)
End
(Full-scale gauge: BSX78-0854).
Marking line
10 to 15 mm
(over the entire edge)
26
No. 2A201-519EN*A
Cut the dotted-line
section with a cutter