Huawei NetCol5000-C030 User Manual page 134

In-row chilled water smart cooling product
Hide thumbs Also See for NetCol5000-C030:
Table of Contents

Advertisement

NetCol5000-C(030, 032, 065) In-row Chilled Water
Smart Cooling Product
User Manual
Figure 5-19 Fan commissioning
Step 6 View the commissioning result.
Issue 06 (2022-12-15)
NO TE
The fan commissioning item is mandatory. After commissioning for a component succeeds,
the system automatically performs commissioning for the next component you selected. If
commissioning fails, startup wizard ends.
Figure 5-20
is displayed if component commissioning succeeds.
Figure 5-20 Commissioning succeeded
Figure 5-21
is displayed if component commissioning fails, which ends
startup wizard commissioning.
Figure 5-21 Commissioning failed
Copyright © Huawei Digital Power Technologies Co., Ltd.
5 Power-On Commissioning
125

Advertisement

Table of Contents
loading

This manual is also suitable for:

Netcol5000-c032Netcol5000-c065

Table of Contents