Huawei IDS1000 User Manual page 20

Container data center single-zone fire extinguishing system
Table of Contents

Advertisement

IDS1000 Container Data Center
User Manual
Figure 3-2 Setting active output for alarms
Step 2 Check the connections of the monitoring cables for reporting the single alarm, composite
alarm, and general fault.
The gas extinguishing controller adopts the passive output to report the alarms, and reports alarm signals
to the management system through the network cable.
Figure 3-3 Correct cable connections for the general fault cables (4, 5), single alarm cables (6, 7),
and composite alarm cables (8, 9)
Step 3 Set the solenoid valve test mode.
Issue 01 (2014-3-15)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3 Power-On Commissioning
Figure 3-3
shows the correct cable connections.