Huawei IDS1000 User Manual page 27

Container data center single-zone fire extinguishing system
Table of Contents

Advertisement

IDS1000 Container Data Center
User Manual
Prerequisites
Procedure
Step 1 Commission the VESDA.
Release some smoke to the protected zone using a smoke pistol and observe the reaction of
the VESDA.
Step 2 Check whether the gas extinguishing controller is in the automatic mode (the controller has
two modes: automatic and manual).
The AUTO indicator lights up when the controller enters automatic mode, and the MANUAL
indicator lights up when the controller enters manual mode. The positions of the indicators are
as shown in
Issue 01 (2014-3-15)
You have completed the power-on for the fire extinguishing system.
The monitoring system is working properly.
Smoke and heat generators have been prepared.
The main task involves commissioning of fire extinguishing association, which can be
operated only by professionals in this field.
Before commissioning the system, ensure that all control cables to solenoid valve drivers
have been disconnected. This prevents the fire extinguishing equipment from
malfunctioning due to improper manual operations or incorrect cable connections, and
further prevents accidental damage. After the commissioning is complete, reconnect the
solenoid valves.
Before commissioning the system, perform the jumper operation for the passive output.
Otherwise, the 6 A fuse (5D) on the main board will be damaged.
If a blow drier is used to simulate the high-temperature scenario, do not get too close to the
detector to avoid the damage of the detector probe caused by high temperature.
Figure
3-12.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3 Power-On Commissioning
21

Advertisement

Table of Contents
loading

Table of Contents