Hardware Power-On Commissioning - Huawei IDS1000 User Manual

Container data center single-zone fire extinguishing system
Table of Contents

Advertisement

IDS1000 Container Data Center
User Manual
Before the power-on of the container data center fire extinguishing system, check all the fire
extinguishing components one by one by following the preceding check methods and items.
----End

3.3 Hardware Power-On Commissioning

Prerequisites
Procedure
Step 1 Switch on the input circuit breaker for the VESDA power box in the corresponding protected
zone. For details, see the Container Data Center Initial Configuration Guide and Container
Data Center Power-On Commissioning Guide.
Step 2 Complete the power-on commissioning for the VESDA. For details, see the delivered
VESDA documents.
If multiple VESDAs are configured in the protected zone, follow the preceding power-on
operations to power on their hardware.
Step 3 Switch on the input circuit breaker for the gas extinguishing controller in the corresponding
protected zone. For details, see the Container Data Center Initial Configuration Guide and
Container Data Center Power-On Commissioning Guide.
Step 4 Turn on the main power and backup power switches for the controller to power on the gas
extinguishing controller.
Issue 01 (2014-3-15)
You have completed the power-on check.
You have obtained the Container Data Center Initial Configuration Guide and Container
Data Center Power-On Commissioning Guide.
You have obtained the documents delivered with the fire extinguishing devices.
Figure 3-11
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
shows the positions of the switches.
3 Power-On Commissioning
19