Powering Off And Maintaining A Smart Cooling Product In Icooling Linkage Mode - Huawei NetCol5000-C Series User Manual

Simple configuration in-row chilled water smart cooling product
Hide thumbs Also See for NetCol5000-C Series:
Table of Contents

Advertisement

NetCol5000-C030 In-row Chilled Water Smart Cooling
Product
User Manual (Simple Configuration)
Figure 4-57 Importing a certificate
Step 2 Tap Browse... next to Upload CA certificate file.
Step 3 Select CA certificate file to be imported.
Step 4 Upload local certificate file and key file in turn in the same way.
Step 5 Enter Key password and Confirm key password.
Step 6 Tap Submit.
----End
4.5.13 Powering Off and Maintaining a Smart Cooling Product in
iCooling Linkage Mode
Context
Procedure
Step 1 On the Teamwork Settings screen, reduce the values of Total number of units and Number
of running units by 1 respectively.
Step 2 Respectively change the values of Teamwork unit address to 3 and 4 for smart cooling
products No. 4 and No. 5.
Step 3 Power off and maintaining smart cooling product No. 3.
Step 4 Respectively change the values of Teamwork unit address back to 4 and 5 for smart cooling
products No. 4 and No. 5.
Issue 09 (2020-01-10)
The screenshot is for reference only. The actual UI display prevails.
When a chiller and micro modules work in iCooling linkage mode, the power-off
maintenance for an smart cooling product under a micro module must be performed in a
specific way to avoid impacts on the entire chiller linkage.
This section uses maintaining smart cooling product No. 3 under a micro module that has
five smart cooling products as an example to describe the operation procedure.
Step 2
and
Step 4
are optional.