1. Assemble the FM/WM Base-F, Base-R and WM Support.
WM Support
FM/WM Base-F
2. Refer to
Figure 2-40 Floor-Mount Spacing Guide on this page
holes for 10 mm anchor bolts (locally procured).
Mark and drill the four holes required to install the FM/WM Base.
3. Using anchor bolts, secure the FM/WM Base to the floor.
2-26

Figure 2-39 Bases and Support of the Battery Box

AC inlet
side
Front side

Figure 2-40 Floor-Mount Spacing Guide

FM/WM Base-R
for required spacing before drilling
Four Anchor bolts
(M10 mm)
Wall
Anchor bolt location
: Maintenance space
Unit : mm