No.
Action
Now open the integrated
STARTER project.
5.
To do this, double-click on
"Commissioning".
Then establish an online
6.
connection and carry out a
download.
When using the extended safety
functions, the hardware
replacement must be
acknowledged after the
download.
7.
To do this, please press the
"Acknowledge hardware
replacement" button.
Then copy from RAM to ROM.
8.
Then go offline.
9.
Now carry out a power-on reset.
To complete commissioning, go
back online, load the
10.
configuration into the PG and
save it.
PROFIsafe SLS Override
Version 1.0, Entry ID: 81682475
6 Commissioning the application
Remark
POWER OFF/ON
57