Commissioning Checklists; Mechanical Installation Checklist; Electrical Installation Checklist - ABB ACS5000 User Manual

Water-cooled
Hide thumbs Also See for ACS5000:
Table of Contents

Advertisement

7.6

Commissioning checklists

This checklist is designed to help you prepare the drive and associated
equipment for commissioning.
7.6.1

Mechanical installation checklist

1)
Drive is aligned according to drive layout drawing (if delivered in
several transport units) and installed according to the
instructions in this user manual (3BHS799208 E01 Rev E).
2) Silicon sealant is applied across roof plate gaps.
3) Roof joints are installed.
4) Pipe joints are orientated and torqued correctly.
5) Roof attachments are installed (if applicable).
6) Busbars are installed and torqued correctly.
7) Raw water piping is completed and pipes are flanged to the
drive (if applicable).
8) Raw water supply is ready.
9) Visual inspection:
• No badly affixed or damaged components
• No foreign objects left in the cabinet
• No dirt, dust or moisture in the cabinet
7.6.2

Electrical installation checklist

1)
Types and cross sections of control cables suitable for the signal
type and signal level.
2) Types and cross sections of power cables selected according to
the ABB power cable specification.
3) Pulse encoder cable shields are connected to the shield earthing
point and not connected directly to the pulse encoder interface
(applies only to drives with pulse encoder interface).
4) Cable entries prepared according to the instructions in the user
manual (3BHS799208 E01 Rev E).
5) Control cable screens and conductors are connected as
instructed in the user manual, labeled appropriately, and the
customer side connections are completed.
6) Heating cables (if supplied) connected
3BHS799208 E01 REV E
ACS5000 WATER-COOLED USER MANUAL
07 COMMISSIONING
120/186