ABB ACS580MV Commissioning Manual page 54

200kw to 6300 kw,3.3kv to 11 kv
Hide thumbs Also See for ACS580MV:
Table of Contents

Advertisement

54 Standard Commissioning Process
Please operate the converter according to the description of "DriveStartup".
Loading the DSP software manually to power modules
Necessary tools: 5.5 VDC power, USB to POF cable and fiber cable.
Install the Tera term programing tool, select the default components.
Check and confirm the drive has been discharged and door lock is released.
Open the INU door and then switch off the control power supply.
Connect the POF link to power module and USB to PC.