70 Standard Commissioning Process
Refer to the motor nameplate for the following settings. Whenever possible, enter the
values exactly as shown on the motor nameplate.
According to the requirement of customer and project side, set the parameters which
are specific for the project:
a. Operation mode, in parameter group 19.