ABB ACS580MV Commissioning Manual page 73

200kw to 6300 kw,3.3kv to 11 kv
Hide thumbs Also See for ACS580MV:
Table of Contents

Advertisement

Press emergency off button on front door, fault AFEB Emergency OFF button pressed
is active. Release emergency off button, the fault should deactivated.
Press ON button on front door, MCB should be closed. Press OFF button on front
door, MCB should be opened.
Press ON button on front door, MCB should be closed. Press emergency off button on
front door, MCB should be opened and fault AFEB Emergency OFF button pressed is
active. Release emergency off button, the fault should deactivated.
Press ON button on front door, MCB should be closed. Wait more than 3 seconds,
Fault E110 DC link charging timeout should activate, MCB trips.
Zoom out the graph. Verify that the MCB control and feedback signals respond in the
correct sequence.
Save measurement in the project. Then attach plot to report.
Standard Commissioning Process 73