Save all the files in project folder and attach to the report.
According to customer preferences, set the control panel language, parameter 96.01
Language.
Save the parameter backup in ACS-AP-W/S panel. Option: Menu/Backups/Create
backup.

SD card data backup

Copy the Date from the SD memory card to PC.
Refer to
Maintenance
"Replacing the SD memory

Spare parts software version

Before leaving the site, the customer spare parts are to be checked against the bill of
material. If spare parts have not been ordered at all, the commissioning report is to be
marked accordingly.
Spare parts of the customer containing software (BCON, ACS-AP-W/S, CVMI2, IO
Controller, Control hub) are to be updated with the versions of the software and the
parameters used in the converter.

Customer training

If not agreed by contract otherwise, the subjects listed below can be used as a guide when
organizing on-site training of operational staff. The training can be based on the
of
ACS580MV Hardware Manual
in
ACS580MV Hardware Manual
card".
(2UBB004520).
Standard Commissioning Process 85
(2UBB004520), section
Operation