11.2

Check before powering on for the first time

Check before powering on for the first time
Before the first power-on, check that the SIMATIC Drive Controller and the SINAMICS
components are correctly installed and wired.
Installation and wiring
● Have the required minimum clearances for heat dissipation been provided?
● Are all front connectors wired according to the circuit diagram and inserted in the correct
connection?
Grounding and chassis concept
● Is the protective conductor terminal on the SIMATIC Drive Controller connected to the
protective conductor?
● Have all cable shields been applied?
● Are the required equipotential bonding cables connected with low impedance to the
affected plant units?
Further information
You can find information on assembly/installation and commissioning of SINAMICS S120
components in the SINAMICS S120 manuals and in the EMC Installation Guide.
(https://support.industry.siemens.com/cs/ww/en/view/60612658)
SIMATIC Drive Controller
System Manual, 11/2019, A5E46600094-AA
11.2 Check before powering on for the first time
Commissioning
191

Advertisement

Table of Contents
loading

Table of Contents