3.
Step 4 Connect power cables to the server and power on the server. Connect a network cable, a VGA
cable, or USB devices as required.
----End

4.4.2 Installing with Adjustable Guide Rails

Adjustable guide rails are for a cabinet with a depth of 543.5 mm to 848.5 mm (21.40 in. to
33.41 in.) between the front and rear mounting bars.
The 2288H V5 servers are not stackable when adjustable guide rails are used.
Step 1 Install the adjustable guide rails.
1.
Issue 04 (2018-09-04)
Figure 4-5 Installing the server
When the two mounting ears of the server come into contact with the mounting bars on
the cabinet, tighten their captive screws to secure the server. See (2) in
Position a guide rail horizontally in contact with the mounting bars and hook it onto the
cabinet. See (1) in
Figure
NOTE
The three holes in each mounting ear of a guide rail should be within 1U boundary lines.