System Operation; Power-On Process - Huawei SmartLogger1000 User Manual

Hide thumbs Also See for SmartLogger1000:
Table of Contents

Advertisement

SmartLogger1000
User Manual
About This Chapter
This topic describes how to start the SmartLogger and set the initialization parameters.

5.1 Power-on Process

This topic describes how to check the SmartLogger before power-on and how to power on the
SmartLogger.
5.2 Setting Initialization Parameters
When starting the SmartLogger for the first time, set initialization parameters on the
monitoring panel. The initialization parameters include system language, system time, the
search address segment for the RS485 port, and the Ethernet parameters.
5.1 Power-on Process
This topic describes how to check the SmartLogger before power-on and how to power on the
SmartLogger.
Checking Before Powering On the SmartLogger
Check and ensure the following before powering on the SmartLogger.
Power-on Process
Power on the devices in the following sequence: Inverter > SmartLogger > PC terminal.
Step
1
Issue 04 (2013-12-15)
All cables are intact and well insulated.
All cables are of proper size.
All cables are correctly connected and secured.
The PC terminal refers to a PC where the NetEco1000 is installed.
Operation
Perform the requirements mentioned in
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
5

System Operation

Checking Before Powering On the
5 System Operation
35