Figure 6-35 Installing top frames
Step 7 Install mounting plates.
Figure 6-36 Installing mounting plates
----End
6.3.3 Installing the UPS + Top Outlet Kit
●
●
Issue 03 (2021-08-03)
If the top outlet kit is configured, installation against a wall is supported.
The following procedure applies to installation against a wall. If cabinets are
not installed against a wall and there is operation space at the rear of the
cabinets, you need to install the cabinet combination screws at the rear and
the anchor screws at the bottom.
Copyright © Huawei Technologies Co., Ltd.
6 Installation
98