Installing The Ups + Top Outlet Kit; Installing Cabinets - Huawei UPS5000-H User Manual

400 kva-800 kva. 100 kva power modules
Hide thumbs Also See for UPS5000-H:
Table of Contents

Advertisement

UPS5000-H-(400 kVA-800 kVA)
User Manual (100 kVA Power Modules)
Figure 6-78 Installing mounting plates
----End

6.4.3 Installing the UPS + Top Outlet Kit

6.4.3.1 Installing Cabinets

Installation on the Floor
Ensure that the installation floor is level.
Step 1 Determine the cabinet installation positions on the floor based on the holes in the
marking-off template for floor installation.
Issue 03 (2021-08-03)
If the top outlet kit is configured, installation against a wall is supported.
The following procedure applies to installation against a wall. If cabinets are
not installed against a wall and there is operation space at the rear of the
cabinets, you need to install the cabinet combination screws at the rear and
the anchor screws at the bottom.
NO TICE
NO TE
● A: mounting holes on the channel steel
● B: mounting holes on the floor
Copyright © Huawei Technologies Co., Ltd.
6 Installation
126

Advertisement

Table of Contents
loading

Table of Contents