8.3 Recommissioning

For recommissioning work to be carried out, the following prerequisites must be fulfilled and the preparatory 
tasks must have been completed.
Tools
No tool necessary
1.
The work or troubleshooting on QWIK‑PURE
2.
The compressed air supply and voltage supply have been established.
3.
The Modbus connection has been established.
Illustration
Prerequisites
Material
No material necessary
Preparatory tasks
is complete.
®
Commissioning work
Description / explanation
1. Slowly open the condensate feed to the
QWIK‑PURE
3 sec
2. Press and hold down the ON/OFF button on the
FRC for 3 seconds.
0 The FRC switches from standby mode to
Protective equipment
Always to be worn:
.
®
normal mode.