Initial Commissioning - Beko QWIK-PURE 15 Installation And Operation Manual

Table of Contents

Advertisement

QWIK-PURE
®

8.2 Initial commissioning

For initial commissioning work to be carried out, the following prerequisites must be fulfilled and the 
preparatory tasks must have been completed.
Tools
No tool necessary
1.
Assembly of the QWIK‑PURE
2.
Electrical installation of the QWIK‑PURE
Illustration
NOTE
3 sec
3 sec
64 | 124
Prerequisites
No material necessary
Preparatory tasks
is complete.
®
Commissioning work
Configuring the number of filter cartridges!
Entering the wrong number of filter cartridges may result in property damage, 
environmental damage, or impaired operation.
Make sure to set the correct number of filter cartridges being used.
Material
is complete.
®
Description / explanation
As soon as the power supply is established, the
status LED FILTER CARTRIDGE SELECTION and the
LED NUMBER OF FILTER CARTRIDGES will flash 
green.
1. Press the Service button and hold it down for
3 seconds in order to set the number of filter 
cartridges being used.
0 The LED NUMBER OF FILTER CARTRIDGES
will switch from the current flashing number 
to the next higher number (e.g., from 1 to 2).
2. Repeat this step until the correct number of
installed filter cartridges is set.
Installation and operation manual
Protective equipment
Always to be worn: