2. PROCEDURE
This section explains the procedures for installing the PABX system. The installer should follow the procedure
shown in the following flowchart. In the flowchart, a NAP (NEC Action Procedure) Number is denoted to the right
side of each step. The NAP Number refers to the details for each procedure.
CHAPTER 3
Page 14
Revision 1.0.1
START
UNPACKING
MARKING AND DRILLING
INSTALLATION
OF
MAIN EQUIPMENT
INSTALLATION
OF
PERIPHERAL EQUIPMENT
CONNECTION
OF
BATTERIES
CABLE RUNNING
TO THE MDF
TERMINATION OF
CABLES ON THE MDF
SWITCH SETTING
OF
CIRCUIT CARDS
A
Figure 3-3 Procedure Flowchart
AD-25182501
NAP- 200-001
NAP- 200-002
NAP- 200-003
NAP- 200-004
NAP- 200-005
NAP- 200-006
NAP- 200-007
REFER TO CIRCUIT CARD MANUAL