● During welding, use a silver copper welding rod containing 5% silver. Check
that the welding joints are in good condition, without poor welding.
● To avoid burning the internal components, other pipes, thermal insulation
foam, cables, and labels, take protective measures, such as spreading wet cloth,
around the welding joints.
● Do not use face-down bonding when welding.
Figure 9-9 Removing the filter dryer
Step 4 Install the new filter dryer.
● When welding a new filter dryer, identify the arrow on the filter dryer. The
arrow direction should be the same as the refrigerant flow direction.
● Do not use face-down bonding when welding.
1.
2.
3.
Issue 04 (2022-06-30)
NO TICE
NO TICE
Remove the rubber plug from the port of the filter dryer.
Install the filter dryer in the unit and weld copper pipes at both ends.
Reinstall the hold hoop.