Step 3 Check the type and quantity of fittings against the packing list. If some fittings are
missing or do not comply with the models in the packing list, record the
information and contact the supplier immediately.
----End

4.3.2 Concrete Platform Scenario

Prerequisites
The evenness of concrete platforms is critical to equipment installation. Ensure
that the height (altitude) difference of all platforms does not exceed 5 mm.
Context
Table 4-4 Hoisting precautions
Stage
Before hoisting
During hoisting
Issue 04 (2022-06-30)
NO TE
● Do not remove the plastic packing materials before connecting pipes and cables to
prevent dust and other foreign matter from entering the unit.
● After pipes and cables are connected, take dustproof measures in a timely manner
based on site requirements.
NO TICE
Precautions
Ensure that the crane and steel ropes provide the required
bearing capacity.
The doors of equipment to be hoisted are closed.
Ensure that the steel ropes are securely connected.
Ensure that the weather condition is good without wind
when equipment needs to be hoisted outdoors.
The ambient wind speed must be lower than 10 m/s.
Do not allow any unauthorized people to enter the
hazardous areas and never stand under the crane arm
during hoisting.
Ensure that the crane is properly located and avoid long-
distance hoisting.
Keep the equipment stable and horizontal during hoisting,
and ensure that the diagonal gradient of the equipment is
within 5 degrees.
Lift and land equipment slowly to prevent shock to
equipment inside it.