4.1.3 Installation Precautions

To ensure the optimal operating condition and longest service life, install the unit
correctly as required.
Equipment Installation Precautions
Equipment Room Layout Requirements
Figure 4-1 Layout of top pipe routing (1)
(1) FusionCol8000-C
Issue 05 (2022-12-15)
Do not expose the unit to strong sunlight in summer. Otherwise, the thermal
insulation panels may be deformed.
Do not stack units.
Install the equipment according to the design drawing and reserve space for
maintenance.
Thermal insulation measures should be applied to outdoor water pipes to
prevent drainage blockage or insufficient water supply due to freezing.
The top of the unit should be sealed during installation (before power-on)
with baffle plates or plastic bags to prevent dust on the top of the unit or
inside the unit.
Before installation, check that the installation environment meets
requirements and check whether buildings need to be altered to facilitate
pipe routing, cable routing, and ventilation duct layout.
Ensure that the equipment room provides good heat insulation, and the walls
and floor are dampproof.
To ensure good ventilation, do not place the equipment in the corner of a
room or at the end of a long and narrow room.
During system operation, all doors and windows of the equipment room
should be closed to reduce the additional load of the unit.
Install the equipment in a spacious place.
The equipment should be placed as far away from offices as possible, and
noise control measures should be taken.