SmartLogger2000-(10-C, 11-C)
User Manual
Reactive Power Control
Because of permission restriction, log in as Special User. Choose Settings > Reactive Power
Control to access the target page.
The remote scheduling command sent by the SmartLogger controls the reactive power output
of the PV plant in analog input mode. Set Reactive Power Control Mode to AI/DI remote
control.
Before setting Reactive Power Control Mode to AI/DI remote control, ensure that
connections between the SmartLogger and the remote terminal control system are correct.
Figure 8-15 AI/DI remote control
8.2.4 Communication Scheduling
Communication scheduling applies to PV plants in China, where an independent power
control device delivers a scheduling command to the SmartLogger over a communication port.
Issue Draft A (2017-02-15)
Power station total rated power (Pn) is the maximum on-grid power of the PV plant agreed by the
PV plant and the power grid company. Confirm this parameter value with the power grid company
and set it correctly.
Grid connection point voltage level (Un) is the voltage level at the connection point between the
PV plant and the power grid. Set this parameter based on the power grid status.
Set parameters under Cos(Phi) direct, Q/P curve, and Q/U curve in sequence.
If Active Power Control is set to Dry contact remote control, Reactive power control mode
cannot be set to AI/DI remote control.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
8 Power Grid Scheduling
177