Figure 8-2 Marking the hole positions for installing a cable tray support
Step 5 Drill a hole in each mounting hole position using a hammer drill, as shown by (1) in
8-3.
Each base must have four installation holes. Preferentially drill the outer four mounting
holes. If steel bars in the concrete platform block the drill bit, drill the inner mounting
holes.
When you drill a hole using a hammer drill, keep the drill bit perpendicular to the ground
and hold the drill stock firmly with both hands to prevent irregular drilling and damage to
the ground.
If the ground is too hard and smooth to fix a drill bit in position, use a chisel to punch a pit
before drilling.
Step 6 Rotate the nut onto the expansion tube to prevent the expansion tube from fluttering, as shown
by (2) in
Step 7 Hammer the expansion bolt into the hole vertically until the flat washer is in close contact
with the ground, as shown by (3) in
Step 8 Remove the nut, spring washer, and flat washer, as shown by (4) in
Issue 02 (2017-01-10)
When you record the hole positions using a marker, ensure that the center of a support base
coincides with the crossing point of the installation reference lines.
There are eight mounting holes in a base. Mark all the hole positions.
Figure
8-3.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
8 (Optional) Installing External Cable Trays
Figure
8-3.
Figure
Figure
8-3.