FusionModule1000A20 IT Solution
Installation Guide (2016.05, AI Version)
Figure 9-26 Installing a VCN500
Step 6 Find the pre-installed power cables with correct labels, and connect the cables to the power
input ports of the VCN500.
Step 7 Connect the network cable reserved for the VCN500 from the LAN switch to the GE1
network port on the VCN500.
Figure 9-27 Connected ports
(1) Ground terminal
(3) Power input port
----End
Follow-up Procedure
Verify the VCN500 installation and ensure that cables are correctly connected.